Radioactive radium waste not an issue  The massive pile of dredge mud that has been sitting between the Seaplane Lagoon and the hangars is now dry enough to be tested to determine the exact contaminant profile and hauled away. 

dredge soil awaiting testing and hauling away

The contaminant of greatest concern to community has been radium-226, the radioactive ingredient once used to make aircraft dials glow in the dark.  Testing revealed that the sediment did not contain elevated radium levels and therefore would not need to be disposed of at a special radioactive waste site.  There were several solid objects, referred to as “buttons,” that were found which contained elevated radium.  Those objects and the surrounding soil were removed for special disposal.

The piles of dredge soil neatly arranged and numbered next to the old Control Tower are waiting to be hauled away to a hazardous waste disposal site. 

Wildlife Refuge Truck Route

In addition to trucking dredge soil to a hazardous waste site, there is a large mound of asphalt that is being trucked onto the wildlife refuge and out to an area where clean soil and fill material is being stored for future use.  This asphalt is from a temporary pad that the Navy laid down in the dredge soil dewatering area.  It was covered with plastic and not contaminated, and now it is no longer needed.

PCB hotspot 

Early this year the Navy began its dredging project to remove contaminated sediment from the northeast and northwest corners of the Seaplane Lagoon. The Seaplane Lagoon ranked as one of the worst PCB sites in the Bay Area according to a regional Water Board study.  The two areas became contaminated with chemicals like PCBs, cadmium, and pesticides that were disposed of through the sewer drains that emptied into the lagoon. The sewer drain system that once carried these chemicals was removed and replaced last year.

removing contaminated dredge soil - Seaplane Lagoon and Maritime ships in background

The Navy’s target completion date for the entire dredging operation was the end of March of this year prior to the arrival of the endangered California Least Terns.  They nest at Alameda Point and feed in the lagoon waters, and disturbing them is prohibited.  The contractor was unable to meet the deadline, and work was halted just as they completed the northeast corner.

Dredging completion date is Spring 2012 

A new dredging company will resume the dredging operation on the northwest corner of the lagoon in early 2012 and complete the operation before the Least Terns come back in April. 

dredge piles waiting to be hauled away - Control Tower in background

 Asphalt from temporary pad at Seaplane Lagoon being hauled to clean fill storage area on wildlife refuge for future reuse (below)

 Dust control on truck route to clean fill storage area on wildlife refuge

, ,

Subscribe and Connect

Subscribe to new posts via the RSS feed. Follow on Twitter and Facebook. View videos on YouTube channel. View photos on Flickr photo site.

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: