Right next to the Main Street Ferry Terminal, between the Oakland Estuary and the Dog Park, is the Navy’s cleanup Site 28, also known as the Todd Shipyards site. The contamination at this site — copper and arsenic, and to a lesser extent lead and hydrocarbons — was not the result of Navy activities, even [...]
January 20, 2012
Precision Dredging at the Pier Area – with video
Designing the workplan for dredging toxic sediment next to Pier 1 at Alameda Point required precision so as not to undermine the stability of the concrete posts supporting the roadway that passes along the pier area. The ground under the water slopes down nearly 40 feet from the cement parking slab adjacent to Wharf Road. [...]
December 30, 2011
Where Alameda Point’s cleanup is at year’s end
The past year had some high points and low points in the cleanup process at Alameda Point. Added delays, including a pile-driving surprise, were balanced out by steady progress. The year saw, among other things, completion of a second Point-wide radiological survey of buildings and structures that identified two building interiors needing radium remediation, [...]
December 18, 2011
Radium Scanning Process at Seaplane Lagoon
Every scoop of dirt that was dredged from the Seaplane Lagoon earlier this year is first sorted into premeasured compartments. The piles are then tested for heavy metals, PCBs, and pesticides. But the piles cannot be tested for radium 226. In order to test for radium, every pile has to be scooped back into a [...]
December 12, 2011
SF Bay Estuary Plan Fails to Connect with Alameda Point
On Sunday, November 11, 2011, Dutra Dredging wrapped up five weeks of maintenance dredging in the channel leading to the Alameda Point docks. This channel is on the south side of Alameda Point where the maritime ships and USS Hornet are docked. Half of the dredge soil went to the in-bay disposal site at Alcatraz. The [...]
November 26, 2011
Case Study – Soil Cleanup Process at Island High/Woodstock Child Development Center
A Case Study in How the Cleanup Process Works In November of 2008, after years of testing, evaluation, and one emergency soil removal action, the Navy issued the final report on what to do in the area where Island High School and Woodstock Child Development Center are located. The area is designated Installation Restoration (IR) [...]
November 21, 2011
Berkeley Lab Site Environmental Plan Released
The Site Management Plan (SMP) for the proposed site of the Berkeley Lab Second Campus at Alameda Point was finalized on November 18. Prepared by the city’s longtime environmental consultant, and signed off on by the Navy and regulatory agencies, the document was prepared in order to mitigate potential risks associated with development of the [...]
November 10, 2011
Video: Alameda Point 2011 Cleanup Update
Dr. Peter Russell, the city’s environmental consultant, made a presentation to the Alameda Reuse and Redevelopment Authority on November 2, 2011, updating them on the status of cleanup at Alameda Point. This video is an edited version with added images. (Note: The phrase “closed site” used in the presentation does not mean off limits. It [...]
October 21, 2011
Cleaning Up Jet Fuel at Building 5
Background The Navy has three cleanup programs at Alameda Point: Superfund, Petroleum, and Radiological. The Petroleum Program takes care of underground concentrations of petroleum, mostly jet fuel, and is organized by corrective action areas. One such area outside Building 5 made it onto the calendar this year. Dumping jet fuel – Building 5, the largest [...]
October 10, 2011
Cleaning up a toxic groundwater plume using heat
There are various methods to clean up groundwater contaminated with solvents and petroleum products. Beneficial chemicals can be injected to neutralize the toxic chemicals. Sometimes bacteria, either those naturally present or some that have been added, can do the job. In some cases at Alameda Point the Navy inserts steel beams called electrodes into the [...]








January 31, 2012
0 Comments